INGEOBRAS Installs BIOBOX Nitrate Removal Pilot Plant in Spain

INGEOBRAS has successfully installed and commissioned a BIOBOX biological nitrate removal pilot plant in Los Alcázares, Spain, as part of the European SEACURE project.

This achievement marks the completion of the design, manufacturing, installation and commissioning stages. It also paves the way for operational monitoring, optimisation and validation under real-world conditions.

The installation forms part of SEACURE DEMO#1, led by INGEOBRAS in collaboration with CETENMA. Its main objective is to validate biological denitrification technology for agricultural waters with high nitrate concentrations.

The pilot is located near the Mar Menor, a Mediterranean coastal lagoon. Reducing nutrient pollution in this area remains a major environmental priority.

BIOBOX Biological Nitrate Removal Technology for Agricultural Water Treatment

The pilot plant incorporates BIOBOX Puremust-SN, INGEOBRAS’ patented biological nitrate removal technology. This solution has already been applied in other nitrate removal applications.

For SEACURE, the technology has been adapted and scaled to treat agricultural runoff from the D7 drainage channel area. These waters contribute to flows reaching the Mar Menor.

Unlike conventional drinking water or industrial wastewater, agricultural runoff presents specific treatment challenges. Therefore, the BIOBOX process has been adapted to address these operating conditions.

Biological denitrification uses microorganisms to convert nitrates into nitrogen gas through a controlled biological process. As a result, it offers a treatment solution for waters containing high nitrate concentrations.

In addition, the BIOBOX system combines several treatment components in a single integrated solution. These include the biological reactor, pretreatment, chemical dosing, instrumentation, pumping, backwashing and control systems.

From Manufacturing to On-Site Installation

The BIOBOX demonstrator was designed as a complete, transportable treatment unit. This design facilitates installation and integration into existing infrastructure.

First, INGEOBRAS manufactured the plant and carried out quality inspections at its facilities. The unit was then transported to Los Alcázares for installation.

Once on site, the team completed unloading, positioning and installation of the auxiliary equipment. Subsequently, hydraulic, electrical and control connections were established with the existing wastewater treatment plant (WWTP).

The installation includes the raw water feed system, biological denitrification reactor and inlet filtration. It also incorporates chemical dosing equipment, process instrumentation and treated water storage for backwashing.

Furthermore, the pilot features integrated control and automation systems.

A Programmable Logic Controller (PLC) and Human-Machine Interface (HMI) allow operators to monitor key process parameters. These systems also manage the pilot’s automated operating functions.

Successful Commissioning and System Verification

During commissioning, INGEOBRAS tested and verified the plant’s main components and operating functions.

The activities included adjusting the inlet flow rate and checking the inlet filtration system. Process sensors and instrumentation were also verified.

In addition, the team configured the chemical dosing system required for biological treatment. The denitrifying biomass was then introduced into the reactor.

Backwashing cycles and automated operating sequences were tested to confirm their correct performance.

As part of this process, the plant operated continuously for more than 24 hours. This test allowed INGEOBRAS to assess system stability and verify process measurements.

It also confirmed the response of pumping, dosing, instrumentation and control equipment under continuous operating conditions.

Following these checks, the installation was considered ready to begin the next demonstration stage.

Moving Towards Real-World Performance Validation

Achieving Milestone 4 marks an important transition for the SEACURE demonstration. Following installation and commissioning, the project now moves towards performance validation under real operating conditions.

During this phase, INGEOBRAS will evaluate BIOBOX Puremust-SN over an extended operating period. The team will also optimise process parameters and collect representative performance data.

The monitoring programme will focus on six key aspects:

  • Nitrate removal efficiency: evaluating treatment effectiveness and overall process performance.
  • Biological process stability: monitoring biomass development and adaptation to operating conditions.
  • Influent water quality: assessing how variations in agricultural runoff affect treatment performance.
  • Filtration and backwashing: verifying operating cycles and their impact on system performance.
  • Chemical consumption: identifying opportunities for resource optimisation.
  • Operation and maintenance: evaluating practical requirements and future scale-up potential.

Together, these activities will help establish the technical and operational performance of the technology.

Moreover, the results will support further process optimisation. They will also provide valuable information on applying biological denitrification to agricultural waters in other locations.

Supporting Nutrient Pollution Reduction in the Mediterranean

For INGEOBRAS, the Los Alcázares demonstrator represents another step in developing and validating its proprietary BIOBOX water treatment technologies.

The company combines engineering, manufacturing, automation, commissioning and process expertise. Through this integrated approach, it develops solutions adapted to different contamination scenarios and operating requirements.

The SEACURE pilot extends this experience to a major Mediterranean environmental challenge: nutrient pollution from land-based activities.

Nutrients transported through drainage channels and other water pathways can eventually reach sensitive aquatic ecosystems. Consequently, reducing these inputs is essential for improving water quality.

SEACURE addresses this issue through an integrated land-river-sea approach. The project develops and demonstrates innovative solutions to prevent, reduce and remediate nutrient pollution across the Mediterranean basin.

Its official title is “Innovative solutions to prevent, reduce and remediate nutrient pollution along the land-river-sea system in the Mediterranean basin”.

The consortium brings together research institutions, public authorities, companies and organisations from several Mediterranean countries.

SEACURE is funded by the European Union under Grant Agreement No. 101157327.

Next Steps: Monitoring, Optimisation and Knowledge Transfer

With installation and commissioning completed, SEACURE DEMO#1 enters its operational monitoring and validation phase.

Over the coming months, INGEOBRAS and its project partners will assess biological nitrate removal performance under real-world conditions.

They will also refine operating parameters and collect technical evidence to evaluate the technology’s potential for wider application.

In the longer term, these findings could support the development of more effective nitrate removal solutions for agricultural waters. Such technologies may contribute to reducing nutrient inputs into vulnerable Mediterranean ecosystems.

Finally, INGEOBRAS will share the main project developments and findings as representative data become available.

This knowledge transfer will help connect research organisations, industry, public authorities and water management stakeholders. It will also support future applications of biological denitrification technology.